05.10.2021
06.31.2021
Camp Lejeune, NC
Camp Lejeune
Saffo Contractors, Inc. was called in to help a MAC Contractor on the Camp Lejeune WTP Rehabilitation Project on an emergency contract. The project consisted of over 50,000 Square Feet of Industrial Blasting & Coating. With only 45 days left on the contract Saffo’s team worked around the clock with 14 hour shifts 6-7 days a week to complete the project on time for the MAC Contractor.
Saffo surface prepped all structural steel to an SSPC-SP 10 and applied 3 coats of Moisture Tolerant Epoxy. Due to the facility operating 24-Hours a day, containment was of utmost importance to prevent dust from escaping into other areas of the facility. Saffo accomplished this by erecting an SSPC Class 2-A containment with a 40,000 CFM Dust Collector.